CONCLUSIONS & RECOMMENDATIONS

Sun Lakes Center is unique among the three campuses of the Chandler-Gilbert Community College (CGCC) in that it serves both college-bound and senior-aged students (with the emphasis on the senior population) and, as such, needs to respond to a more diverse group than the other two. The enrollment figures cited earlier in this report indicate that this campus needs at least double its space by the year 2010. Due to the nature of this site and the land available, a second story 5,600 GSF addition to the existing facility is the only option available at the writing of this master plan. The facility was originally designed for a second floor, according to CGCC Facilities staff and SLEC personnel.

The following system upgrades will need to be addressed with the expansion:

  • Mechanical: Remove and dispose of the existing rooftop mechanical equipment. Based on the final layout of the first floor, it will be determined whether any of the existing ductwork or toilet exhaust ventilation system can be retained.

    Provide multiple new air cooled heat pump units, with a total cooling capacity of approximately 35 tons, with packaged rooftop units to serve the second floor, and split system (or packaged rooftop units) to serve the first floor. Provide programmable thermostats.

    If the toilet rooms on both floors can be "stacked" a new common exhaust system could serve both. Otherwise, provide separate exhaust systems.
  • Plumbing: New roof drain piping system should connect to existing, if possible. Provide new plumbing fixtures as well as the sanitary waste and vent piping system for second floor, with piping interconnection to existing.

    Provide domestic water piping to second floor toilet room. Existing service and meter size to be confirmed. Provide new electric domestic water heater.
  • Fire Protection: Extend piping from existing fire riser to provide sprinkler coverage for the second floor.
  • Electrical Distribution: The existing electrical distribution system is not adequately sized for the proposed addition. The electrical load will more than double when the additional lighting and HVAC loads are considered along with new elevators. A new service will be required that can be installed on the exterior of the building. Existing panels can be resupplied from the new service and new panels added to the second floor for the new loads associated with the expansion. A building of this size would typically be supplied with a 120/208V service. The estimated load, assuming split system and rooftop, packaged system heat pumps, is approximately 30 VA per square foot or 300 kVA. Based on this assumption, a 1,000 A, 120/208V service will be required.
  • Fire Alarm: A new fire alarm system will be required. An addressable system capable of controlling and monitoring the duct detectors at the HVAC units and the elevators will be required.



CGCC Logo
Maricopa Community Colleges